There are major differences in the way the HRSGs behind GTs are tested compared to conventional boilers, even WHRBs. The HRSG is treated as part of a combined cycle power plant (CCPP) instead of a stand-alone steam generator.
• For HRSGs behind GTs PTC 4.4 is applied and not PTC 4.
• The performance test is a direct test.
TABLE 1.8 Differences in Measurements of Losses and Credits between PTC 4.1 and PTC 4
|
• No separate efficiency guarantees are demanded of HRSGs as the guarantees for total CCPP are given.
• HRSG is required to only demonstrate the (1) gas pressure loss and (2) steaming conditions of HP, IP, and LP steam circuits at the specified loads with the GT exhaust gas supplied at specified quantities and temperatures.
• Steam pressures and temperatures are noted along with inlet and exhaust gas pressures and temperatures of the HRSG. It is normal to adopt this direct method and perform the test that lasts at least 2 h.
• The plant must be running at nearly the same load as the test load, for some time before and some time after the test, to attain a steady-state condition.
• There should be no blowdown during test.
• The drum levels at the beginning and end of the test should be nearly the same.
• The frequency of test readings can be at more than 10 min for all primary readings except for flowmeter readings that must be recorded every 5 min.
• The code specifies the measuring tolerances (Table 1.9).
TABLE 1.9 Tolerances for Direct Measurement of Parameters (PTC 4.4)
|
Note: Variation of any station observation from reported average test condition during a test run. |